Imperial fears year delay to Kearl tar sands project
Syndicated from Oil Sands Truth on Tue, 2008-05-13
In sections:
Imperial fears year delay to Kearl oilsands project
Claudia Cattaneo, Financial Post Published: Thursday, May 08, 2008
CALGARY -- Imperial Oil Ltd. said in Federal Court Thursday its $8-billion Kearl oilsands project faces a delay of a year or more if a key water permit pulled by the federal government isn't quickly re-instated.
"It took nine months to get this piece of paper," lawyer Munaf Mohamed, of Fraser, Milner Casgrain LLP, argued before Justice Douglas Campbell. "What
is sufficient in terms of the sting of the lash?